0 inspection and startup checklist, 1 inspection, Nspection – Emerson Liebert FPC User Manual

Page 29: Tartup, Hecklist, Inspection, Warning

background image

Inspection and Startup Checklist

25

3.0

I

NSPECTION

AND

S

TARTUP

C

HECKLIST

3.1

Inspection

___ 1. Confirm that the exterior of unit is undamaged (including cables and receptacles, if

furnished).

___ 2. Confirm that service and ventilation clearances are adequate. (See Figures 1 through 3.)
___ 3. Remove accessible exterior and internal panels.
___ 4. Inspect all wire and conductor insulation for damage.
___ 5. Check all transformer terminal connections for tightness. Retorque if necessary.
___ 6. Check all breaker connections for tightness. Retorque if necessary.
___ 7. Check all terminal block connections for tightness. Retorque if necessary.
___ 8. Check transformer mounting bolts for tightness. Retorque if necessary.
___ 9. Remove any foreign objects from the components or the interior area of the unit.

Make sure air passages on transformers are clear and free of debris.

___ 10. Check that the intake and exhaust air screens are clean and free of obstructions.
___ 11. Replace internal and exterior side panels, leaving access to circuit breakers for the following

start-up procedure.

Unit Serial Number
Unit Model Number
Date

!

WARNING

All equipment inspection procedures are to be performed with power to the unit turned off

and locked out.