beautypg.com

3 activation, Switch the circuit breaker on – SMA SB 2800i Installation User Manual

Page 23

background image

Installation Guide

Installation

SB2800i-11:SE0504

SMA Regelsysteme GmbH

21

5.3 Activation

You can activate the Sunny Boy 2800i when:

• The AC (grid) cable has been correctly connected.
• All the DC (PV) strings have been connected and all unused

DC plug connectors on the underside of the inverter have
been closed with the protecting caps.

• The lid has been tightly screwed on.

Proceedings for activation

1. Switch the circuit breaker on.

2. Check whether the LEDs indicate trouble-free operation of the

Sunny Boy 2800i based on the following table. If this is the
case commissioning has been successfully completed.

.