Requirements

Check the following requirements before commissioning:

• Automatic Switch Box is mounted securely to the wall
• All cables are correctly and completely connected
• All cables are tightly enclosed by the cable glands

Commissioning procedure

1. Loosen screw caps of all fuse elements.
2. Insert headed sleeves into all fuse elements.
3. Insert fuses into the screw caps.
4. Install screw caps including fuse into the fuse elements.
5. Lock Automatic Switch Box with the switch cabinet key.
6. Attach enclosed label visibly in the consumer system.