Connection procedure – SMA AUTOMATIC SWITCH BOX M User Manual

Page 26

background image

Electrical Connection

SMA Solar Technology AG

26

AS-BoxM-IEN091711

Installation Guide

Connection Procedure

1. Select suitable cable opening for the cable of the power supply counter and poke a hole in it

with a pointy device.
The cable has to be tightly enclosed by the cable gland after insertion.

2. Pull the cable of the power supply counter through the opening into the Automatic Switch Box.
3. Connect PE to the "X1/Load Meter" connection terminal according to the label.
4. Connect L1 and potentially (in case of 3-phase loads) L2 and L3 to the "X1/Load Meter"

connection terminals according to the label.

5. Connect N to the "X1/Load Meter" connection terminals according to the label. The second

connection terminal "N" is not assigned.

☑ The consumption meter is now connected.