Problem
Cause and corrective measure
The Cluster Controller does not send
any data to Sunny Portal.
The data transmission is incorrectly configured.
Corrective measures:
• If the Cluster Controller is not yet registered in
Sunny Portal, register the Cluster Controller in
Sunny Portal (see Section 11.1, page 60).
• Test the connection to Sunny Portal (see
• Check the settings for Sunny Portal (see Section 11,
An error has occurred in the LAN.
Corrective measures:
• Check whether the network settings of the individual
network components are correct. Adapt the network
settings if required.
• Check whether the network components are
defective or damaged. Replace defective or
damaged network components.
After replacement of the Cluster Con-
troller, two systems with the same sys-
tem name appear in Sunny Portal.
The system has been registered twice in Sunny Portal. The
new Cluster Controller logs into Sunny Portal with a new
system identifier. Sunny Portal creates a new system for
this system identifier, even if you have given the system the
same name.
Corrective measures:
• Assign the system identifier of the old system to the
replacement device (see Section 11.6, page 63).
• In the replacement device, enter the e-mail address of
a user who has administrator rights for the system in
Sunny Portal.
• In Sunny Portal, delete the new system created by the
replacement device.
18.3 Restarting the Cluster Controller via the User Interface
1. Log into the Cluster Controller as Installer.
2. Select the Cluster Controller in the system tree and select the menu Settings in the device
menu.
3. Select the parameter group Device > System.
4. In the field Initiate device restart, select [Execute].
☑ The Cluster Controller is restarted. The start-up procedure can take up to two minutes.