33

6.4.2 Connecting the Data Cables for Control and Measuring

Signals

Procedure:

1. Plug the data cable for control and measuring signals (red) for the master of the main cluster in

the pin connector Mstr/L1.

2. Plug the data cable for control and measuring signals for Slave 1 of the main cluster in the pin

connector Slv1/L2.

3. Plug the data cable for control and measuring signals for Slave 2 of the main cluster in the pin

connector Slv2/L3.

6.4.3 Connecting the Data Cables for Communication

Procedure:

1. Plug the black data cable for the communication between Sunny Island and Multicluster Box in

the pin connector ComSyncIn. Leave the terminator plugged into the pin connector
ComSyncOut.

2. Plug the end of the data cable in the pin connector ComSyncIn of a Sunny Island inverter in

the main cluster. Since all Sunny Island inverters (master and slaves) of the main cluster are
connected via a communication bus, the Multicluster Box can be connected to a slave or the
master of the main cluster.