6  Electrical Connection

SMA Solar Technology AG

28

MC-BOX-6_12-BE-en-20

Operating Manual

Procedure:

1. Prepare the connection cables (see Section 6.2 "Preparing the Cables", page 24).
2. Connect the grounding conductor and N to the terminal X3 PV-System as labeled.
3. Connect L1, L2 and L3 to the terminal X3 PV-System as labeled.

6.3.4 Connecting the Sunny Island

Fuse of the Sunny Island inverters
Each Sunny Island is fused by a circuit breaker inside the Multicluster Box.

• Multicluster Box 6.3-11: 40 A
• Multicluster Box 12.3: 32 A

Optimum mounting location
If the Multicluster Box and the Sunny Island inverters are operated under different ambient
conditions, the circuit breakers for the Sunny Island inverters may trip more often.

• To ensure optimum operation, mount and install the Multicluster Box and the Sunny Island

inverters at the same location.