6 commissioning, 1 preparations, 2 start-up – Watson-Marlow SP40 User Manual
Page 26: Commissioning 6.1, Preparations, Start-up

COMMISSIONING
23
6
COMMISSIONING
6.1
Preparations
•
Connect the electric motor in conformance with
the locally applicable rules and regulations.
Have the electrical installation work carried out
by qualified personnel.
•
The pump casing is filled with a Bredel Genuine
Hose Lubricant. If necessary refill lubricant via
the breather/vent plug (refer to section 7.3).
•
Set the actuator switch in the pumping position.
•
In case of pneumatic actuator check if the
actuator response is good (refer to section
8.6.3).
•
Check the rotation of the rotor.
•
Check that the number of shims corresponds
with your application, refer to section 11.1.8.
•
For adjusting the compression force of the
hose, refer to section 7.8.
•
Make sure that there are no obstructions such
as closed valves.
6.2
Start-up
•
Switch on the hose pump.
•
Check the rotation of the rotor.
•
Check the capacity of the hose pump. If the
capacity differs from your specification, follow
the instructions in chapter 10 or consult your
Bredel representative.
•
Check the hose pump in accordance with points
1 to 4 of the maintenance table from section
7.1.