Initial Start Up

1. Remove front panel and evaporator cover. Check

machine for any packing or wires rubbing moving

parts. Note location of control board in upper left

corner of the machine’s front.

2. Switch on the electrical power to the machine.

Observe that some of the control’s indicator lights

glow and its display shows O.

3. Open the water supply valve.

4. Push and release the ON button. The code display

will begin to blink F.

The purge valve opens, the water pump starts and

the inlet water valve opens to add water to the

reservoir. In a few seconds the purge valve closes

and the water pump stops. Water will flow into the

machine until the reservoir is full. The hot gas valve

and harvest assist device will activate, then the

compressor and water pump will start. If it’s an air

cooled model the fan motor(s) will begin to turn a few

moments after the compressor starts. The display

will show a continuous F. Five seconds later the hot

gas valve will close and the harvest assist device

will return to its standby position. Warm air will be

discharged from air cooled models.

5. Observe the Ready for Harvest indicator light. It

may blink early in the cycle, that is normal. The

control will ignore that signal for the first 6 minutes

of freeze.

6. During the Freeze cycle move the curtain and

observe that the SW1 or SW2 light on the control

board blinks On when the curtain moves away

from the evaporator and Off when returned to its

normal position.

Note: Moving the curtain during the Freeze cycle has

no affect on control function, but will cause water to

flow into the cube chute.

7. When enough ice has frozen, the Ready for

Harvest indicator light will be on steady. After it’s

been on steady for a few seconds Harvest will

begin.

The display shows an H. The hot gas valve opens, the

air cooled fan motor(s) shut off and the harvest assist

mechanism is activated. The purge valve opens to

drain some water, when it does the inlet water valve

opens to refill the reservoir. After a few seconds the

purge valve closes but the inlet water valve continues

to fill the reservoir. Harvest continues until the ice

is released as a unit and forces the curtain to open.

When the curtain opens it signals the controller which

returns the unit to a freeze cycle.

8. Check the ice harvested for proper bridge

thickness. The ice bridge is factory set at 1/8 inch.

If needed, adjust bridge thickness. Do NOT make

it too thin.

9. Return the front panel and evaporator cover to

their normal positions and secure to the machine.

10. Instruct the user in the operation of the machine

and its maintenance requirements.

11. Fill out and mail the warranty registration form or

register it on line at Scotsman-ice.com.

Typical Ice Making Cycle Times (minutes).

Listed times are for clean machines in proper

installations. Cycle length at startup will be longer until

the system stabilizes.

Model

70

o

F air / 50

o

F.

water

90

o

F. air / 70

o

F.

water

C0322A

10-12

14-16

C0322W

9-11

10-12

C0522A

11-13

16-18

C0522W

13-15

13-15

C0330A

9-11

12-14

C0330W

8-10

9-11

C0530A

12-14

16-18

C0530W

10-12

11-13

C0630A

9-11 1

1-13

C0630W

7-9

10-12

C0722A

13-15

19-22

C0830A

10-12

13-15

C0830W

11-13

12-14

C1030A

9-11

11-13

C1030W

9-11

10-12

This manual is related to the following products: