beautypg.com

Control panels operations, Main switch i/o, Operation of cooling unit (procool 10, procool 30) – Kemppi Protig 501L User Manual

Page 16

background image

16 – PROMIG 501, PROMIG 511/0537

© KEMPPI OY

P21

R21

P22

R22 P23

S22

S21

S24

S25

S26

R23

S22

2.11. MAIN SWITCH I/O

When you turn the main switch of the PRO power source into I-position, pilot lamp close to it is lighted

and the equipment is ready for welding. The equipment is returned to that welding method with which

the welding was last carried out before the main switch was turned to zero position.

Always start and switch off the machine with the main switch, never use the

mains plug as a switch.

2.12. OPERATION OF COOLING UNIT

(PROCOOL 10, PROCOOL 30)

Operation of cooling unit is controlled in such a way that pump is started when welding is

started. After welding stop pump is rotating for approx. 5 min cooling the liquid to ambient

temperature.
Read in operation instructions for the PROCOOL 10 / 30 unit the trouble situations of the liquid

circulation system and protection against torch etc. damage.

3. CONTROL PANELS OPERATIONS

3.1. MC CONTROL PANEL 6263501

MIG basic operations

Welding method selection (S21): MIG two-sequence procedure, MIG four-sequence

procedure, MMA
Control mode selection (S22): local, remote, gun
Local controls: wire feed speed/MMA current (R21), welding voltage (R22)
Controls for MIG and MMA welding dynamics (R23)
Digital displays: wire feed speed (P21), current (P22), voltage (P23)
Retrieval of last used welding values (S23)