8

Mechanical Installation

1. Position the scoreboard at the front of the beams, and lift it to the desired height.
2.
Place a C-channel against the upper rear flange of the scoreboard next to each beam.
3.
With the C-channel as a template, use a

9

/

16

" bit to drill holes in the upper rear flange

of the scoreboard cabinet where the rods will pass through. The rods should be as
close to the beam as possible.

4. Push the rods through the holes in the rear flange of the scoreboard cabinet and into

the C-channel, and then thread

1

/

2

" square nuts onto the rods inside the C-channel.

5. Place clamping angles over each pair of rods and secure with

1

/

2

" lock washers and

hex nuts.

6. Make final adjustments in the positioning of the scoreboard to ensure it is flush and

level, and then firmly tighten all of the

1

/

2

" hex nuts.

7. Repeat steps 2-6 for the lower rear flange of the scoreboard for every beam.

I-Beam Clamps

Mounting hardware includes C-channels; washer plates; I-beam clamps;

1

/

2

-13 x 3.5" bolts;

self-drilling screws; and

1

/

2

" square nuts, hex nuts, flat washers, and lock washers. Refer to

Figure 9 and Drawing A-1129110 in Appendix B.

Note: I-beams must have a flange thickness of

3

/

16

" –

3

/

4

". If flange is thicker than

3

/

4

",

longer bolts will be required at added expense.

Figure 9: I-Beam Clamp Mounting Method, Front Rotated View