Installation
This chapter describes CBS 212A mounting, interconnections, and calibration.
Mounting
When installing a CBS 212A Current Boost System, provisions must be made for the mounting of the
Current Boost Module and the Current Transformers (CTs). The CBS 212A must be mounted where the
environmental conditions do not exceed the specifications given in the Specifications chapter.
Current Boost Module
The Current Boost Module is convection cooled and should not be mounted near heat-generating
equipment or inside a totally enclosed cubicle where the temperature could exceed the operating limit.
Vertical mounting is recommended to obtain optimum convection cooling. Mounting and panel drilling
dimensions are provided in Figure 3.
Figure 3. Outline and Panel Drilling Dimensions
CBS 212A
Installation