Hardware Preparation and Installation

This chapter describes the preparation before installing the RTM, the applicable environmental
and power requirements, and the actual installation and removal of the RTM.

2.1

Unpacking and Inspecting the RTM

Shipment Inspection

To inspect the shipment, perform the following steps:

1.

Verify that you have received all items of your shipment:

MVME721X RTM

One printed copy of Quick Start Guide

One printed copy of Safety Notes Summary

Any other items ordered

Damage of Circuits

Electrostatic discharge and incorrect installation and removal of the blade can damage
circuits or shorten its life.

Before touching the blade or electronic components, make sure that you are working in
an ESD-safe environment.