4.
Creating Task via Testing Configuration
When performing tests with your DUT on NuApps-IGMP-RM for the first time, you have to create a new set 
of test settings to run the test. 
Before starting to create a new task via New Testing Configuration, please be sure that:
¾
All module cards (such as XM-RM751, XM-RM761, or XM-RM781) are installed on chassis (such as 
NuStreams-2000i/600i) properly. 
¾
The chassis (such as NuStreams-2000i/600i) is powered-on and is connected to a PC (or IPC 
module installed on NuStreams-2000i) according to “3.1. Starting NuApps-IGMP-RM”. 
To start using New Testing Configuration, please click File on the Menu Bar, and choose New Testing 
Configuration… as shown in the figure down below. 
A “Reserved Config” window will pop up. All module cards that are installed on the chassis will be 
displayed here. 
 
 