Creating task via testing configuration – Xtramus NuApps-IGMP-RM V1.2 User Manual
Page 28
4.
Creating Task via Testing Configuration
When performing tests with your DUT on NuApps-IGMP-RM for the first time, you have to create a new set
of test settings to run the test.
Before starting to create a new task via New Testing Configuration, please be sure that:
¾
All module cards (such as XM-RM751, XM-RM761, or XM-RM781) are installed on chassis (such as
NuStreams-2000i/600i) properly.
¾
The chassis (such as NuStreams-2000i/600i) is powered-on and is connected to a PC (or IPC
module installed on NuStreams-2000i) according to “3.1. Starting NuApps-IGMP-RM”.
To start using New Testing Configuration, please click File on the Menu Bar, and choose New Testing
Configuration… as shown in the figure down below.
A “Reserved Config” window will pop up. All module cards that are installed on the chassis will be
displayed here.
28
E-mail: [email protected]
Website: www.Xtramus.com
XTRAMUS TECHNOLOGIES
®