Power consumption management – NEXCOM NISE 90 User Manual

Page 64

background image

Copyright © 2013 NEXCOM International Co., Ltd. All Rights Reserved.

50

NISE 90 User Manual

Appendix A: Power Consumption

Power Consumption Management

Purpose

The purpose of the power consumption test is to verify the power dissipation
of system, and the loading of power supply.

Test Equipment

PROVA CM-07 AC/DC CLAMP METER

Device Under Test

DUT: sys#1/

Test Procedure

1. Power up the DUT, boot into Windows XP
2. Entering standby mode (HDD power down)
3. Measure the power consumption and record it.
4. Run Burn-in test program to apply 100% full loading
5. Measure the power consumption and record it.

Test Data

Sys #1

+24V

Full-Loading Mode

1.42A

Total

17.04W

Standby S1 Mode

N/A

Total

N/A