SOR 1710 Compact Level Switch User Manual
Page 2
2/8
Form 916 (03.14) ©SOR Inc.
Physical Installation
The 1710 must be mounted so that the centerline is within 3º of horizontal. The
conduit connection centerline must be within 3° of vertical and the nameplate at 12
o’clock. Switch actuation cannot be reversed by rotating the unit 180°.
Pipe support hangers or stands should be used where necessary.
All isolation valves must be fully open during service, as restricted valves may
cause erroneous level switching.
Remember external chamber piping should be short, straight and unrestricted.
Pipe must be of a diameter equal to or greater than the process connection
diameter.
Valves and other equipment between the chamber and process must be of the same
diameter or larger than the process connection diameter to allow adequate liquid
flow into the chamber.
Installation shall be carried out by suitably-trained personnel in accordance with the
applicable code of practice e.g. EN 60079-14.
Not following these installation instructions, including pipe and valve
diameter and pipe lengths can affect operation of the switch, including
differential.