NORAC UC4+BC+JD8A User Manual
Page 21
17
2. Remove the rubber bumpers on both
ends of the roll frame (Figure 16).
3. Install the frame target (B09) onto the
parallel lift frame. The mounting bolt
should be close to the vertical member
of the frame facing forwards. See Figure
15 and Figure 16.
4. The frame target should be 41” (104cm)
from the bottom of the sensor as
shown in Figure 18.
The frame target (B09) should be
mounted to a frame member
that does NOT rotate with the
boom.
5. Install the spring target (B12) onto the
boom center section 16” (41cm) down
from the bottom of the sensor as
shown in Figure 17.
The spring target (B12) must be
mounted to a frame member
that does move with the boom.
Figure 17: Target Location
6. Assemble the roll sensor mounting
bracket as shown in Figure 18.
7. Install the roll sensor bracket on the T-
shaped black intermediate frame, as
shown in (Figure 17). The required
mounting hardware is included with the
bracket.
The bracket rod is designed to
slide in the bracket collar to
allow for sensor alignment
required in Step 8.
The sensor should be mounted
between the parallel lift arms and
the wheel in a position that will
not interfere with folding.
The sensor should not be behind
the wheel.
Figure 18: Roll Sensor Mounting
Bracket
Mount Frame
Target as close
to the vertical
member as
possible.