TESC Operator's Manual, Rev 1.0
21
CANNON®
Calibrating the TESC System
Calibration procedure
Use the following procedure to calibrate the Watlow® controller.
1. Turn on DV2T and TESC. If the Watlow® controller starts to run a program, press the
red
EZ
button to halt the test. (Steps symbol indicates a running program.)
Note:
The 8 hour TESC calibration program lowers the temperature of
the sample to the desired soak temperature and maintains that
temperature for 8 hours, allowing the operator to run multiple
calibration tests.
2. Load the appropriate 8 hour TESC temperature calibration program into the Watlow®
controller:
a. Connect PC to Watlow® controller using RS-485 to USB cable.
b. Launch Watlow® configurator program:
Start Menu > EZ-ZONE Configurator > EZ-
ZONE Configurator
.
c. Select
Download a configuration file to a device
. Click
Next
.
d. Select the COM port to which the Watlow® controller is connected. Click
Next
.
e. Select
Load Program from File
.
f. Select program:
•
For –26 °C, select file
D2983-TESC-Caliboffset-8h-Minus26-WatlowPgm.wcf
.
•
For –40 °C, select file
D2983-TESC-Caliboffset-8h-Minus40-WatlowPgm.wcf
.
g. Click
Exit
.
3. Autozero DV2T:
a. Remove spindle if present.
b. Lower viscometer to measurement position.
c. Level entire unit if necessary.
d. Select
Next
on the DV2T
AutoZero
screen.
e. When the DV2T indicates AutoZero complete, raise viscometer.