Series 5900 Silicone Structural Glazed Curtain Wall Installation

Section IV: Frame Assembly

Frame Assembly – Silicone Structural Glazed Horizontals

A.)

Assemble shear blocks, splices, anchors, etc., to mullions as required.

B.)

Install and anchor vertical mullions to form the vertical sections per “APPROVED”
shop drawings.
















Rotate the horizontal over the shear

block from the interior of the

system. With the horizontal in

position, fasten with (1) #10-16 X
1” PLFH Tek3 screw on each end of

horizontal, and tighten as required.

¼” X 1 ½” HWHSMS

1” Minimum

Apply sealant to the

face and top of the
shear block as shown.

Filler

#10-16 X 1”

PLFH Tek3

Note: The commercial cut to length tolerance is +- 1/16”.

It is critical to check every 5

th

“UNIT” for location.