Series 5900 Silicone Structural Glazed Curtain Wall Installation

Vertical Adaptor

Horizontal Adaptor

VII: Glazing Adaptors

Installation of Glazing Adaptors at Silicone Structural Glazed Mullions

A.)

Vertical adaptor length without a

mullion expansion joint equal
D.L.O. plus 1”.

B.)

Vertical adaptor length with a
mullion expansion joint, see the

“APPROVED” shop drawings.

C.)

Horizontal adaptor length equal

D.L.O. minus 1/16”.

D.)

Install the vertical
adaptors first, and attach

with #8 X 1 ¼” PLPH SMS

at a minimum of 18” on
center. (Seal fastener

heads with sealant.)

E.)

Install the horizontal adaptors

between the vertical adaptors.

Installation of Glazing Adaptors at Captured Mullions

A.)

Position the vertical adaptors as

shown.

B.)

Place horizontal adaptors

between the verticals.

C.)

Seat adaptors by applying sealant
to all four corners.

D.)

Cut formula for vertical adaptors
equal D.L.O. plus 1”. Horizontal

adaptors equal D.L.O. minus
1/16”.




Set all adaptors in a continuous

bead of sealant, and seal all
vertical to horizontal adaptor

intersections.

Continuously seal the

gasket raceway with

sealant prior to

installing the adaptors.

Note: Vertical adaptors need a minimum

of 1/8” clearance above the
mullion plug, free from sealant.