STEP #2 ANCHOR FIRST DOOR JAMB
The frame directly adjacent to the door opening will have the first door jamb. This jamb is 3/4” longer
than the typical mullions and extends below the sill down to the top of the floor slab. To maintain Exte-
rior sealant line, apply silicone to the interior surfaces of the door jamb and tool to the condition. The
door frame mullions and anchor clips are shown with the minimum amount of anchor bolts required, for
the purposes of the illustrations. The size, type, spacing, and quantities should be determined on a job-
by-job basis by the responsible engineer.
A. Note: The anchor clip must be slid into the door jamb
before
the frame is secured into the
opening. Ensure the clip is flush with the bottom of the mullion and the top of the condition.
Attach the anchor clip to the door jamb with screws as shown.
B. Drill anchor bolt holes through the clip and into the substrate as required.
Bolt the anchor clip to the condition.
DOOR JAMB
ANCHOR BOLTS
AS REQUIRED
ANCHOR CLIP
ANCHOR CLIP
ANCHOR CLIP
ATTACHMENT
SCREWS
Seal and Tool interior of Door
jamb to the condition