Bolted wind load anchors – EFCO S5500 Outside Glazed User Manual

Page 21

background image

EFCO CORPORATION 6/2012

PART NO. Y550

Series 5500 Outside Glazed Installation Instructions

Section III: Typical Anchorage Methods

STEP #9 INSTALL FRAME COMPONENTS – BOLTED WIND LOAD ANCHORS

For installations with multi-spans, follow applicable notes from step 8. Match drill the mullion

through the

CENTER

of the set of slots in the anchor.

NOTE: The holes must be a minimum of 1” from the back of the mullion in order to clear any steel

reinforcement located inside of the system as may be required on a job specific basis.
Use a bolt with a flat washer at the bolt head end. At the nut end of the bolt, use a flat washer then

spring lock washer next to the nut as shown. Shim each bolt as shown.

Important:

The nut must be tightened sufficiently to completely compress the spring lock washer.

Back the nut off a quarter to half turn to allow free movement of the connection.

The threads of the bolts must be “staked” or Loctite must be used to prevent the nut from loosening

from the bolt. Remove the temporary alignment screws. Refer to the approved shop drawings for

anchor locations, bolt sizes, welding requirements, and other job specific information.

BUILDING

STRUCTURE

STEEL ANCHOR PER

SHOP DRAWINGS

Bolt anchor to building

structure per approved

shop drawings.

Match drill through

center

of slots.

TEMPORARY ALIGNMENT SCREW (#12 X 1” TEK

SCREW) Note: Screw

must

be removed from

wind load anchor after bolt installation to allow
free movement.

BOLTED WIND LOAD ANCHORS

HIGH IMPACT

POLYSTYRENE

HORSESHOE SHIMS

AT EACH BOLT