Chapter 2 setup, Unpacking and inspection, Setup – Bird Technologies MSCC7 Series-Manual User Manual
Page 17: Ge 3, S 3, 5, 9, Unpacking and inspection setup
![background image](/manuals/583708/17/background.png)
3
Chapter 2
Setup
Unpacking and Inspection
1. Carefully inspect shipping container for signs of damage.
2. Do one of the following:
z
If the shipping container is damaged, do not unpack the unit. Immedi-
ately notify the shipping carrier and Bird Electronic Corporation.
z
If the shipping container is not damaged, unpack the unit. Save ship-
ping materials for repackaging.
3. Inspect unit for visual signs of damage.
Note: z
If there is damage, immediately notify the shipping carrier
and Bird Technolgies Group.
Setup
Setup consists of three basic steps: moving the Cal Cart into position, install-
ing the vent plugs, and connecting AC power and the RF line. These steps are
explained in more detail below.
WARNING
Do not attempt to lift the cart by the handle.
WARNING
All vent plugs must be installed on the load at all times when
the unit is operating or cooling. Failure to do so could result
in an explosion or severe burns.
WARNING
Never attempt to connect or disconnect RF equipment from the
transmission line while RF power is being applied.
Leaking RF energy is a potential health hazard.
CAUTION
Check the electrical code for proper AC hookup prior to
operation of the unit. Make sure the neutral or return hookup
is only used for that purpose.
CAUTION
Changing the sensor’s connectors will invalidate calibration data, and may
reduce the maximum power rating of the unit.