Installation Checklist

Use the following installation checklist to ensure proper handling.

Installation procedure

Complete

Comments

Maximum cable length not exceeded

Bending radius not exceeded

Maximum tensile load not exceeded;

proper pulling techniques used

Cable not squeezed or bent

Cable installed without loops in raceways

Cable protected from sharp edges

Fiber cable installed in separate raceways from
copper

Cable connector cleanliness maintained

Cable connector finger tight to transceivers

ATTENTION

Hand tighten connectors. Do not use tools to tighten connectors as they
may cause damage to cables and inhibit signal transmission.