5
Start-Up
Prior to start-up ensure that equipment intended to be powered by the APC
transformer is connected properly to the transformer. Failure to do so may
cause the UPS to go into bypass mode for up to 30 seconds before beginning
normal operating prodedure.
1. Plug the transformer L6-30 connector into the UPS.
2. Connect all additional equipment to the transformer and the UPS.
3. Turn on all connected equipment.
4. Turn on the power to the UPS by pressing the button located on the front panel
of the UPS.
All equipment intended for use with the APC transformer must be connected to
the transformer prior to using the Cold Start function.
41063-264-01(1)
‘ •
•
•
•
Œ
1. Verify that the transformer input cord
Œ
is
unplugged.
2. Remove the voltage selection switch cover
•
.
3. Set the input voltage selection switch
Ž
to match
the utility voltage of 208 V or 240 V.
a. If 240 V utility is used, program the UPS output
for 240 V. Refer to the UPS user manual.
b. Install the voltage selection switch cover
•
.
4. Plug applicable load equipment into the PDU
receptacles
•
on the transformer.
5. Plug the transformer input cord
Œ
into the
appropriate PDU receptacle on the rear of the UPS.
6. Verify that the output circuit breakers
•
are ON.
7. Verify that the input circuit breaker
‘
is ON.
Ž
•