The commissioning steps in detail
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
6.2
The commissioning steps in detail
In the following sections, the individual commissioning steps are described.
Follow the instructions of these sections step by step in order to commission your system.
6.2.1
Planning the bus topology
Before installing a PROFINET network, make a diagram of the network.
How to plan the bus topology for your configuration
1. Create an overview of the planned PROFINET network with all field devices to be
integrated.
2. Start with the I/O master.
3. Add the other field devices (I/O devices) below.
6.2.2
Installing field devices
For the installation of a field device, follow the mounting instructions for the respective device.
More detailed information about how to work with the Lenze Engineering tools can be
found in the corresponding manuals and online helps.
Mounting instructions of the field devices
Observe the safety instructions.