2 analog inputs, 3 digital input, 4 functional test – JUMO 705021 mTRON T - Analog Input Module, 8-Ch. Operating Manual User Manual
Page 26: Digital input, Functional test, 4 electrical connection, 2 analog inputs 4.3.3 digital input

4 Electrical connection
26
4.3.2
Analog inputs
4.3.3
Digital input
4.4
Functional test
The voltage supply must be tested on completion of the electrical connection:
Startup
The check described above completes the process of installation and electrical connection. For
startup, use the additional documentation (operating manual or system manual).
The "Introduction" section of this document contains an overview of all documentation for the
measuring, control, and automation system.
Connection
Input
Terminals
Symbol and terminal designation
RTD temperature probe
2-wire circuit
1
2
3
4
5
6
7
8
1 and 2
3 and 4
5 and 6
7 and 8
9 and 10
11 and 12
13 and 14
15 and 16
1, 3, 5, 7, 9 , 11, 13, 15
2, 4, 6, 8, 10,12, 14, 16
Connection
Input
Terminals
Symbol and terminal designation
Digital input DC 0/24 V
1
17 and 18
17
18
U
+
-
x
Signal
Meaning
LED "P" (Power, green) is lit
The module is being supplied with voltage
through the side contacts.
LED "P" (Power, green) is not lit
The module is not supplied with voltage or there
is a problem with the electrical function of the
LED.
Remedy:
•
Check the voltage supply to the side contacts
of the preceding module (top contact +24 V,
bottom contact GND).
•
Check voltage supply at the "+24 V" and
"GND" terminals of the base unit or router
module.
•
Check power supply unit and connection be-
tween the power supply unit and the base unit
or router module.
If the "Power" LED does not light up despite a
voltage supply being present, the module insert
or – if the bus board inside the case is faulty – the
entire module must be replaced.