1. Summary of components
1-11
Festo P.BE-SPC11-DNC-EN en 0012NH
Measuring system type MLO-POT-...-LWG (
7 )
S Use measuring system type MLO-POT-...-LWG (piston-rod
potentiometer) with the DNC-... .
The measuring system must be longer than the cylinder
stroke used. There must be an electric reserve. The fol-
lowing stroke lengths are possible, depending on the
measuring system length:
Measuring system length
[mm]
Max. usable stroke length
[mm]
100
90
150
140
225
215
300
290
360
350
450
440
600
590
750
735
S Mount the measuring system and the drive symmetrically,
so that the centre of the measuring system stroke co-
incides with the centre of the complete drive stroke (see
also System manual type P.BE-SPC11-SYS-...).
S For earthing, connect the earth strip to the flat plug of the
measuring system and to the earthing connection of the
SPC11 (see Fig. 1/1).
The earth strip in included with the measuring system.