Installation instructions - all applications – AZEK Pavers User Manual
Page 7

Page 7
Mix multiple
pallets of the
same color within
an installation
to disperse any
potential slight
variations in shade.
LAYING AZEK PAVERS
+ 3” Grid
16” Grid
+
8” Grid
11” Grid
REMINDER:
Installation grids must
be orientated to allow
the pattern of pavers
to interlock grids in
both directions.
One example of cutting grids for optimal layout
Installation Instructions - All Applications
2
• Choose your starting point based on the project dimensions
and desired look, keeping in mind any cutting that may need to
happen.
• Begin by laying a handful of AZEK’s patented installation grids
in the arrangement that matches your pattern to ensure pavers
overlap grids in both directions.
• To increase installation speed, order extra installation grids to get
started.
• Bring over grids full of pavers, dump them next to where they will
be placed into the grid, and place the empty grids into place.
• If mixing colors, bring over the ratio of colors being used and
dump them in front of the person laying pavers. For example, for
a pattern using 40% Boardwalk, 40% Olive, and 20% Waterwheel.
The carrier would bring over 2 grids of Boardwalk, 2 grids of Olive,
and 1 grid of Waterwheel each time.
• Begin laying pavers in the desired pattern; ensuring pavers are
overlapping grids in both directions.
• When the edge is reached, grids can be cut to fit using a jigsaw or
miter saw, and a low tooth count wood ripping blade.
• Continue laying pavers until all full pavers (i.e. not cut or trimmed)
are installed.
• If the perimeter grid is less than 4", cut 4" or 8" off of the interior
adjacent grid to increase the size of the perimeter grid. See
example below.