Chatsworth Products Hot Aisle Containment User Manual
Page 38

Aisle Containment Manual, Rev. 2.0
___
June 2013
Chatsworth Products
38
4.
Locate the frame panels by aligning with the shallowest cabinet.
ATTACH ADJACENT PANELS AND LATERAL BRACE VERTICAL BEAMS
1. Attach neighboring duct frames using M6X16 carriage bolts and M6 flange nuts.
2. A lateral brace should be installed every 48-
60” (1200-1500mm) along the cabinet aisle.
Where required, the vertical beam of the brace is installed between neighboring duct panels
as shown.
3. The vertical beam of the lateral brace should be cut 2.5inches [64mm] less than the cabinet
to ceiling distance to accommodate for the upper lip seal.
4. Fasten carriage bolts through upper most and lower most flange holes that have clearance
for the bolt.
Shallow Cabinet