beautypg.com

Tube installation sequence – Hired-Hand Universal Ray Tube Heaters: AG2 Series Rev.11-07 User Manual

Page 11

background image

Key

11

Tube Installation Sequence

20 Foot

50 Foot

60 Foot

30 Foot

40 Foot

AG2

Series

Figure 2.5

Tube Installation Sequence

Burner Control Box with
16” Burner Tube

Uncoated Steel Primary
Combustion Chamber

2.0

Installation

Tube Sequence

Heater Length

Important! The combustion chamber & radiant tube sections must be installed in the following order.

NOTE: Refer to the Tube Heater General Manual, Chart 3.6 (page 22) for secured reflector joints.

Uncoated Aluminized Steel Secondary
Combustion Chamber Location
(150,000 BTU/H models only)

Uncoated Aluminized Steel
Secondary Combustion Chamber

(150,000 BTU/H models only)

Hot-Rolled Steel Radiant
Emitter Tube or ALUM-AO

Tube Clamp

Baffle Location

Uncoated Aluminized Steel Secondary
Combustion Chamber Location
(150,000 BTU/H models only)