10

Brocade Encryption Switch Hardware Reference Manual

53-1001117-02

2

Table 1

describes the main installation and setup tasks and the estimated time required for each

task. These time estimates assume a prepared installation site and appropriate power and network
connectivity.

TABLE 1

Installation tasks, time, and items required

Installation task

Time estimate

Items required

Site preparation and unpacking the switch

30 minutes

None

Installing the rack mount kit

30 minutes

Refer to the Fixed Rack Mount Kit Installation
Procedure
, the Slide Rack Mount Kit
Installation Procedure
, or the Mid-Mount
(Switch) Rack Kit Installation Procedure.

Mounting and securing the switch in the
rack

15 minutes

Installing power cables and powering on
the switch,

10 minutes

Power cables (provided in the accessory kit).

Establishing serial connection, logging on
to the switch, and configuring the IP
addresses.

20 minutes

Serial cable (provided in the accessory kit).
Workstation computer with a serial port or
terminal server port and a terminal emulator
application (such as HyperTerminal).
Ethernet IP addresses for the switch.

Installing an Ethernet cable, opening a
Telnet session, and configuring the switch
domain ID, date and time, and additional
system parameters. Verify and backup
configuration.

20 minutes

Ethernet cable for Telnet access.
Refer to the Fabric OS Administrator’s Guide.

Installing SFPs. Attaching and managing
fiber optic cables.

15 minutes

SFP optical transceivers. Fiber optic cables
and cable ties.