Brocade Encryption Switch Hardware Reference Manual (Supporting Fabric OS v6.1.1_enc) User Manual
Page 24

10
Brocade Encryption Switch Hardware Reference Manual
53-1001117-02
2
describes the main installation and setup tasks and the estimated time required for each
task. These time estimates assume a prepared installation site and appropriate power and network
connectivity.
TABLE 1
Installation tasks, time, and items required
Installation task
Time estimate
Items required
Site preparation and unpacking the switch
30 minutes
None
Installing the rack mount kit
30 minutes
Refer to the Fixed Rack Mount Kit Installation
Procedure, the Slide Rack Mount Kit
Installation Procedure, or the Mid-Mount
(Switch) Rack Kit Installation Procedure.
Mounting and securing the switch in the
rack
15 minutes
Installing power cables and powering on
the switch,
10 minutes
Power cables (provided in the accessory kit).
Establishing serial connection, logging on
to the switch, and configuring the IP
addresses.
20 minutes
Serial cable (provided in the accessory kit).
Workstation computer with a serial port or
terminal server port and a terminal emulator
application (such as HyperTerminal).
Ethernet IP addresses for the switch.
Installing an Ethernet cable, opening a
Telnet session, and configuring the switch
domain ID, date and time, and additional
system parameters. Verify and backup
configuration.
20 minutes
Ethernet cable for Telnet access.
Refer to the Fabric OS Administrator’s Guide.
Installing SFPs. Attaching and managing
fiber optic cables.
15 minutes
SFP optical transceivers. Fiber optic cables
and cable ties.