Cont ...

Pipework Connections (Hot Water)
(RGFL, RGDFL and ESFL range)

These pumps should have a minimum of 22 mm pipework throughout the system.
The supply must be air free and connection to the cylinder can be made by one of the

following methods shown.

When method of connection is to be via the expansion pipe, the cold water storage

cistern should be at least 1 metre above the top of the hot water cylinder.

ELECTRICAL INSTALLATION

WARNINGS:

The electrical installation must be carried out in accordance with the

current national electrical regulations and installed by a competent

person.

In the interests of electrical safety a 30 mA residual current device

(R.C.D.) should be installed in the supply circuit. This may be part of

a consumer unit or a separate unit.

Before starting work on the electrical installation ensure the power

supply is isolated.

This appliance must be earthed.

The motor and wiring must not be exposed to water.

Do not allow the supply cord to contact hot surfaces, including the

motor shell, pump body or pipework. The cord should be safely

routed and secured by cable clips.

The motor fitted to this pump is suitable for a single phase 230V, 1 phase, 50Hz supply.

It is thermally protected by an integral auto resetting thermotrip for your safety. The pumps
are rated for the duty listed in the technical specification section.

Fig. 9

Off expansion
pipe with rising
28 mm offset
reducing to
22 mm pipework
to pump and
expansion pipe.

Off expansion
pipe with rising
22 mm offset
and 22 mm
pipework to
pump.

Off vertical
expansion pipe
with 22 mm
pipework to
pump.

Factory installed G ¾
secondary tapping
with 22 mm pipework
to pump.

or

Site installed G ¾
Essex Flange with
22 mm pipework to
pump.

Warix Flange with
22 mm pipework
to pump.