1. LAY OUT CLEAR REINFORED POLY DOOR ON A FLAT
SURFACE.
2. INSERT ROLL-UP TUBE INTO ROLL-UP DOOR SLEEVE.
3. SECURE THE POLY DOOR TO THE DOOR TUBE USING
ROLL-UP TUBE CLIPS APPROXIMENTLY EVERY 36".
FIGURE 1
4. SET THE ROLL-UP DOOR WITH TUBE IN THE CRADLE.
5. LIFT THE FREE END OF THE POLY DOOR MATERIAL TO THE
TOP OF THE DOOR FRAME AND SECURE WITH WIGGLE WIRE.
BE SURE TO CENTER THE DOOR OVER THE OPENING. FIGURE 2
NOTE: IT IS IMPORTANT THE ROLL UP DOOR TUBE IS STILL
RESTING IN THE CRADLES DURING THIS PROCEDURE.
6. USING DOOR GROMMETS AS A VERTICAL GUIDE, DRILL 6 - 3/8"
HOLES THROUGH DOOR JAMBS AND WIGGLE WIRE BASE.
INSERT CARRIAGE BOLT WITH THREADS TO THE OUTSIDE
AND TIGHTEN WITH LOCK WASHER & HEX NUT. FIGURE 3
INSTALL BALL KNOBS AND ATTACH BUNGEE CORDS OVER
BALL KNOB FIGURE 4
7. CHECK OPERATION OF DOOR BY UNHOOKING BUNGEE CORDS
AND ROLLING UP THE DOOR TO TOP GROMMET ELEVATION, AND
SECURING THE DOOR OPEN BY INSERTING A BUNGEE BALL CORD
THROUGH EACH GROMMET AND WRAPPING THE CORD AROUND
THE ROLLED UP DOOR. INSERT BALL THROUGH LOOP OF CORD
TO SECURE.