IntraCore IC3624PWR Layer 2 PoE Switch with Dual Gigabit

Warning: Make sure you support the switch until all the mounting screws for each bracket is secured to the
equipment rack. Failure to do so could cause the switch to fall, which may result in personal injury or damage to the
switch.

When installing multiple switches, mount them in the rack, one below the other, in any order.

When installation is complete turn to the “Applying Power” section.

3.6.2 Desktop or Shelf Mounting

Follow these steps when planning to use the switch on either a desktop or a shelf:

1. Attach the four adhesive feet to the bottom of the switch.

2. Set the device on a flat surface near an AC power source, making sure there are at least two inches of space on

all sides for proper airflow.

3. Place each device squarely on top of the one below, in any order.

When installation is complete refer to the “Applying Power” section.

3.7 Applying Power

The system’s front panel LED display allows you to monitor the status of the switch. Follow these steps to connect
the switch.

1. Use the supplied power cord and plug the female end directly into the receptacle located at the back of the

device.

2. Plug the other end of the cord into a properly grounded electrical outlet.

3. Check the front-panel LEDs as the device is powered on to be sure the Power LED is lit. If not lit, check that the

power cable is correctly plugged in.

4. Connect the optional redundant power supply to the switch and to an AC power source by following the

instructions for the unit.

Warning: For International use: if you use power other than AC, you must use power cords that meet the appropriate