DAILY START-UP:
1.
Inspect material levels to begin production - resin, hardener and solvent.
2.
Turn On the Main Power
3.
Open the Main Air Inlet supply to system.
4.
Install mix housing, spring and balls into mix housing.
5.
Set the Select switch to Recirc and the Start / Stop to Start;
6.
Adjust the Rate control to the desired output speed. Allow several pump strokes
and inspect return hose in the tank to assure material flow.
7.
The unit is ready to operate
– it is important to perform a periodic ratio check and
material gel test this can done at this time.
8.
Prepare the Dispense gun for operation then set the Select switch to Gun.
MAINTENANCE:
1.
The water trap should be inspected daily, drain water from trap as needed.
2.
Inspect pump piston shafts for material build-up and clean as needed.
3.
Inline filters should be checked weekly and cleaned as needed
4.
Once a month the hydraulic oil reservoir should be checked to be sure the fluid
level is correct.
5.
As noted earlier tighten Recirculation & Dispense gun packing to stop or prevent
leaks.
6.
Recirculate the materials occasionally if the unit is not going to be in use for a
several days. The material in the hoses can be recirculated by using the Ratio
Block.