3.0 Installation,
continued
3.2 Installation, CE-3x2 5K-T
Prior to installation verify the following:
•
All necessary grounding rods and materials are in place.
•
Utility power was run to site in accordance with the NESC (National Electric Safety
Code).
•
Obtained local safety practices for working with high-voltage systems.
•
Gas piping, hardware, supports, and other gas carrying components to the pad location
conform to NFPA standard and local requirements.
Required Tools and Materials:
•
Crane to lift enclosure from shipping pallet and place on pad
•
Key(s) to enclosure doors
• Digital
voltmeter
•
Torque wrench with insulated handle and 7/16" socket
•
7/16” box-end wrench
•
NO-OX or other suitable corrosion inhibiting agent (NCP-2)
•
Silicone sealant GE RTV123 (or equivalent)
•
Phillips screwdriver (for pad shear mounting)
•
5/8" socket for removing pallet mounting bolts
• Hard
hats
• Utility
knife
To prevent injury or death, do not walk, or allow personnel to walk, beneath the suspended
unit. Use steel-toe work shoe protection. Use hard hats at all times during this procedure.
Before lifting, verify the transport path is clear of obstructions.
WARNING!