TeamWork 400 and TeamWork 600 Kits

TeamWork 400

TeamWork 400i

TeamWork 600

TeamWork 600i

HDMI switcher

1 (SW4 HDMI, 4 input)

1 (SW4 HDMI, 4 input) 1 (SW6 HDMI, 6 input)

1 (SW6 HDMI, 6 input)

System controller

1 (IPL T PC1)

1 (IPL T PC1i)

1 (IPL T PC1)

1 (IPL T PC1i)

Cable Cubby 800

1

1

1

1

Power modules

2 US modules included
(4 AC outlets total)

Sold separately
(2 AC outlets total)

2 US modules included
(4 AC outlets total)

Sold separately
(2 AC outlets total)

HDMI “Show Me” cables

4

4

6

6

HDMI cable

1

1

1

1

Switcher control cable

1

1

1

1

Cable Cubby AAP brackets
(three-space)

2 pairs

3 pairs

2 pairs

3 pairs

Cable Cubby AAP brackets
(two-space)

2 pairs

2 pairs

Cable pass-through AAPs
(right, single space)

1

1

Blank AAP plates
(single-space)

2

3

2

3

IEC C14 male power cord
plug (see instructions below)

1

1

Installation Guide

TeamWork Kits Installation Guide

IEC C14 Male Power Cord Plug Installation

When using the IPL T PC1i system controller (International TeamWork kits) you must replace the power plug on the display with
the provided IEC C14 male power cord plug. This plug has a maximum current rating of 10 A and a maximum voltage of 250 VAC.

WARNING:

High Voltage. Failure to follow these instructions may result in serious injury.

Installation and service of the power cord plug must be performed by authorized personnel only.

Observe the correct wire polarity.

Before installation, disconnect the display from the power source or any other device.

NOTE:

The power cord plug shown in the figure is for illustration only. The plug provided may not look exactly the same.

L G N

4. Loosen the screw and remove the top
plate.

1. Cut the existing plug from the
power cord.
2. Remove a suitable amount of
the outer sheath from the
power cord.
Individual wires should not
extend from the back of the
strain relief after the plug is
installed.
3. Strip a suitable amount of the
jacket from the three wires.
There should be just enough
bare metal to wrap around
the screw in step 7.

5. If required, loosen the white plastic wire
clamp.

Ground

(Earth)

Neutral

Live

(Hot)

6. Thread the cord through the strain relief.
7. Use a flat head screwdriver to secure the
individual wires to the correct connector.

8. Secure the wires by tightening the white
plastic wire clamp.
9. Reattach the top plate and screw that were
removed in step 4.

WARNING: Observe the correct wire
polarity (see the diagram to the left).