beautypg.com

Check-out procedure — checklist, Cgs-4e gas-fired water boiler — boiler manual, Installation and service certificate – Weil-McLain GOLD CGS-4E User Manual

Page 31

background image

Part number 550-110-282/1108

31

GOLD

CGs-4E Gas-Fired Water Boiler — Boiler Manual

Check-out procedure — checklist

8

Boiler and heat distribution units filled with water?

Automatic air vent, if used, open one full turn?

Air purged from system?

Air purged from gas piping? Piping checked for leaks?

Correctly sized manifold orifices installed? Refer to manual

Section

2a

to check size and fuel type.

Correctly sized manifold orifices must be used.

Failure to do so will cause severe personal in-

jury, death or substantial property damage.

Followed operating instructions on boiler or in manual

Section

9

for proper start-up?

Verify that the boiler switches to high fire after 60 seconds

of main flame operation.

Proper burner flame observed at high fire? Refer to

Check

burner flame

, manual Section

7b

.

Test limit control — While burners are operating, move

indicator on limit control below actual boiler water tem-

perature. Burners should go off while circulator continues

to operate. Raise setting on limit control above boiler water

temperature and burners should reignite.

Test additional field-installed controls — If boiler has a low

water cutoff, additional high limit or other controls, test for

operation as outlined by manufacturer. Burners should be

operating and should go off when controls are tested. When

controls are restored, burners should reignite.

Test ignition system safety device:
a. Connect manometer to outlet side of gas valve.

b. Start boiler, allowing for normal start-up cycle to oc-

cur and main burners to ignite.

c. With main burners on, manually shut off gas supply at

manual main shutoff gas valve. Burners should go off.

d. Open manual main shutoff gas valve. Manometer

should confirm there is no gas flow.

e. Pilot will relight, flame sensing element will sense pilot

flame and main burners will reignite.

Set limit control(s) to system temperature requirements.

Adjust balancing valves and controls to provide design

temperature to system.

For multiple zones, adjust flow so it is about the same in

each zone.

Verify thermostat heat anticipator (if available) set properly?

Refer to

Field wiring

, manual Section

6

,

Thermostat(s)

.

Cycle boiler with thermostat — Raise to highest setting and

verify boiler goes through normal start-up cycle. Lower to

lowest setting and verify boiler goes off.

Measure natural gas input:
a. Operate boiler 10 minutes.
b. Turn off other appliances.
c. At natural gas meter, measure time (in seconds) re-

quired to use one cubic foot of gas.

d. Calculate gas input:

e. Btuh calculated should approximate input rating on

boiler rating label.

Check manifold gas pressure by connecting manometer to

downstream test tapping on main gas valve. Manifold pres-

sure for natural gas should be 3.5" w.c. and for propane gas

should be 10" w.c.

Observe several operating cycles for proper operation.

Set room thermostat to desired room temperature.

Fill in Installation and service certificate below?

Review all instructions shipped with this boiler with owner

or maintenance person. Return instructions to envelope

and give to owner or place in pocket inside front panel in

boiler.

Installation and service certificate

Boiler model __________________ Series __________ CP number ___________ Date installed ___________

Measured Btuh input ____________________

Installer ________________________ ________________________________ ________________________
(company) (address) (phone)

Installer’s signature: _____________________________________

❏ Installation instructions have been followed.

❏ Check out sequence has been performed.

❏ Above information is certified to be correct.

❏ Information received and left with owner/maintenance person