Gas piping, Cgs-4e gas-fired water boiler — boiler manual, Connecting gas supply piping to boiler – Weil-McLain GOLD CGS-4E User Manual
Page 25

Part number 550-110-282/1108
25
GOLD
CGs-4E Gas-Fired Water Boiler — Boiler Manual
Gas piping
5
Table 4 Pipe capacity for 0.60 specific gravity natural gas
Gas
pipe
length
(feet)
Capacity of pipe for pipe size of:
(Capacity in cubic feet gas per hour)
½”
¾”
1”
1¼”
1½”
10
132
278
520
1050
1600
20
92
190
350
730
1100
30
73
152
285
590
860
40
63
130
245
500
760
50
56
115
215
440
670
75
45
93
175
360
545
100
38
79
150
305
460
150
31
64
120
250
380
Natural Gas:
1. Refer to
Table 4
for pipe length and diameter. Base
on rated boiler input (divide by 1,000 to obtain cubic
feet per hour).
Table 4
is only for gas with
specific
gravity 0.60, with a pressure drop through the
gas piping of 0.30” w.c.
For additional gas pipe
sizing information, refer to ANSI Z223.1 (or B149.1
or B149.2 for Canadian installations).
2. Inlet pressure required at gas valve inlet:
• Maximum: 13” w.c.
• Minimum: 5” w.c.
• Manifold gas pressure: 3.50” w.c. at high fire
(0.90” w.c. at low fire while in low fire at start-
up)
3. Install 100% lockup gas pressure regulator in supply
line
if inlet pressure exceeds 13” w.c.
Adjust for
13” w.c. maximum.
Propane Gas:
1. Contact gas supplier to size pipes, tanks and 100%
lockup gas pressure regulator.
2. Adjust propane supply regulator provided by gas
supplier for 13” w.c. maximum pressure.
3. Inlet pressure required at gas valve inlet:
• Maximum: 13” w.c.
• Minimum: 11” w.c.
• Manifold gas pressure: 10” w.c. at high fire
(3.50” w.c. at low fire while in low fire at start-
up)
Connecting gas supply piping to boiler
1. Remove jacket front panel and refer to
Figure 14
to pipe gas to boiler.
a.
Install drip leg
at inlet of gas connection to boiler. Where local
utility requires drip leg to be extended to the floor, use appropri-
ate length of pipe between cap and tee.
b.
Install ground joint union
for servicing, when required.
c.
Install manual shutoff valve
in gas supply piping outside boiler
jacket when required by local codes or utility requirements.
d.
In Canada
— When using manual main shutoff valve, it
must be
identified
by the installer.
2.
Support piping
with hangers, not by boiler or its accessories.
3.
Purge all air
from gas supply piping.
4. Before placing boiler in operation,
check boiler and its gas connection
for leaks
.
a.
Close manual main shutoff valve
during any pressure testing at
less than 13” w.c.
b.
Disconnect boiler and gas valve from gas supply piping
dur-
ing any pressure testing greater than 13” w.c.
Do not check for gas leaks with an open flame
—
use bubble test. Failure to use bubble test or check for
gas leaks can cause severe personal injury, death or
substantial property damage.
5.
Use pipe dope compatible with propane gases.
Apply sparingly
only to male threads of pipe joints so that pipe dope does not block gas
flow.
Failure to apply pipe dope
as detailed above can result
in severe personal injury, death or substantial property
damage.
Figure 14 Gas supply piping