load, which is dependent on the TSC 80E configuration setting. The factory default setting is
for a “Load Transfer” plant exercise test. The engine will remain operating on load until the
plant exercise time delay period expires, then the load will re-transfer back to the utility supply
following the 2-minute utility return timer. On ATS using TSC 80 controller, the engine will be
automatically re-tested on load every week (i.e.7 days) at the same time of day that the first
test was initiated. On ATS using TSC 80E controller, the engine will be automatically re-tested
as programmed in software. Refer to the TSC 80E manual for further information.

17) On completion of commissioning ensure all controls are left in automatic.

18) If required, forward document or drawing updates to the equipment supplier if revisions are

required and provide the end user with a set of marked-ups to be retained on site.

19) Ensure copies of manuals for the equipment are on site.

20)

Record and forward list of deficiencies to the appropriate parties where applicable.