beautypg.com

Appendix “a – Technicolor - Thomson POWER & CONTROL TS 870 User Manual

Page 47

background image

APPENDIX “A”

THOMSON TECHNOLOGY

©

TYPICAL AUTOMATIC TRANSFER SWITCH

COMMISSIONING PROCEDURES

Model Series TS 870

9087A - 198

th

Street, Langley, B.C. Canada V1M 3B1

Telephone (604) 888-0110

Telefax (604) 888-3370

10) Prior to operating the generator, ensure it is ready to be energized and the site electrical

contractor and/or owner (as required) give authorization to proceed. In preparation for
operation, turn the generator’s engine control switch to the “Automatic” start position.

11) To transfer the generator on load, perform a load test by pressing the Utility Power Fail

Simulate pushbutton “ON” and holding it for approximately 5 seconds until the LED light above
the push button changes state. The engine should start following the 3-second engine start
delay period and the transfer switch will begin transferring to the generator supply once the 2-
second engine warm-up timer expires. Note: The engine warm-up timer will only begin timing
once the generator’s output rises above 85% nominal voltage and 90% nominal frequency.
Once the Utility power switching device opens, the transfer switch mechanism will pause in the
neutral position for the 3-second neutral delay period, then the mechanism will complete the
transfer and close the generator power switching device. To determine correct operation,
observe the following on the TSC 80E faceplate:

i) Generator Source green LED is “ON”

ii) Red LED above mimic bus for the generator source is “ON”

iii) Green “Load” LED is “ON”

iv) Utility Source green LED is “ON”

v) Utility Power Fail Simulate yellow LED is “ON”

vi) Green LED above mimic bus for the Utility source is “OFF”

12) To terminate the test, press the Utility Power Fail Simulate push button on the TSC 80E

faceplate again and hold until the LED above the pushbutton changes state. The transfer
switch will begin transferring to the utility supply following the 2-minute utility return delay
period. Note: the utility return delay timer will only begin timing if the utility voltage is above
85% nominal on all phases. Once the Generator power switching device opens, the transfer
switch mechanism will pause in the neutral position for the 3-second neutral delay period, then
the mechanism will complete the transfer and close the Utility power switching device to return
the load to the Utility source. Once the load has transferred onto the utility source, the engine
will continue to run for the 2-minute cool down time delay period and will then it will
automatically stop.

13) Perform a power outage test by opening the upstream utility feeder breaker. The TSC 80E

controller Utility supply LED lights will de-energize; the generator set will start after the 3-
second engine start delay has expired. The generator should transfer on load as described in
item #12 above.

14) Return the transfer switch to utility power by re-closing the upstream utility breaker. The load

should re-transfer back to the utility supply and the engine should stop as described in item
#13 above.

15) Repeat tests #12 through 14 two (or more) times to ensure correct operation.

16) Automatic Plant Exercise Operation (OPTIONAL): If an automatic weekly plant exercise

feature is desired, press the GENERATOR EXERCISE Mode push button on the TSC 80E
faceplate. Hold the push button “ON” for approximately 5 seconds until the LED light changes
state. Once the mode is initiated, the engine will immediately start and the generator will
transfer on load as previously described. Note: The generator may or may not transfer on