TS 870 TRANSFER SWITCH

PM062 REV 8 10/01/25

12

Thomson Technology

The generator will continue to supply the load until the utility supply has returned.

The retransfer sequence is completed as follows: when the utility supply voltage is

restored to above the preset values (adjustable from 70% to 95% of nominal) on all

phases, a transfer return delay circuit will be initiated. Following expiry of the Utility

Return Timer (adjustable from 0 to 30 min.), the Transfer to Generator Supply signal

will be removed (contact opening), then the Transfer to Utility Supply signal (contact

closure) will be given to the transfer switch mechanism. The load will then retransfer

the load from the generator supply back to the utility supply. Note: A neutral delay

timer circuit will delay the transfer sequence in the neutral position (i.e. both power

switching devices open) until the neutral delay time period expires (adjustable from 0

to 60 seconds).

An engine cooldown timer circuit will be initiated once the load is transferred from

the generator supply. Following expiry of the cooldown delay period (adjustable

from 0 to 30 minutes), the engine start signal will be removed (contact opening) to

initiate stopping of the generator set.

5.2.

SERVICE ENTRANCE AUTOMATIC TRANSFER SWITCH

Note: This applies only to service entrance transfer switches

5.2.1. NORMAL OPERATION

Under normal conditions, the load is energized from the utility supply through the

closed utility transfer power switching device. If the utility power fails, the generator

will start and the load will be re-energized via the closed generator transfer power

switching device.

In the normal operating mode, the Service Disconnect switch shall be in the

“energized” position.

5.2.2.

OVER CURRENT

TRIP

Should the utility power switching device trip open due to an over current condition,

TSC 80E transfer controller will initiate an engine start signal and will permit transfer

of the load to the generator supply. The utility source will be locked out and the load

will remain on the generator supply until the TSC 80E alarm signal is manually reset.

Refer to the TSC 80E Instruction Manual for further details on Transfer Fail

operation.