Page 80

background image

70

G9000 Installation and Operation Manual

EMB

CPMS

CPMC


3.4

OPERATING PROCEDURES

For Parallel Operation system, refer to section “D) MMS Start-up Procedure”.

(Parallel Operation system is herein after MMS [Multi Module System])

A) Start-up Procedure

Before the UPS startup, the internal Bypass line starts to supply the unconditioned bypass

input power to the load if the External input (or Bypass) Circuit Breaker is closed. Be

extremely careful with closing the External input (or Bypass) Circuit Breaker.

Confirm the position of the circuit protectors (CPMC, CPMS and EMB) located at the upper

part of the cabinet (FIGURE 3.8).

1) CPMC and CPMS: ON; 2) EMB: OFF.

FIGURE 3.8 Circuit protectors location

a.) Verify that the External Bypass Input Circuit Breaker for each unit is closed.

(user supplied)

b.) Verify that Battery Disconnect Circuit Breaker (CB2) is opened or in tripping position.

c.) If a dual source is feeding the UPS, close the External AC Input Circuit Breaker manually (user

supplied).

d.) The LCD panel boots up automatically, and the screen will show that the Load is powered by

bypass line.

e.) On the LCD panel, select “OPERATION” tab, and then press the “STARTUP GUIDANCE” button

to continue UPS start-up. (Refer to Figure 2.3)

f.) Follow the “STARTUP GUIDANCE” accordingly until the completion of the inverter startup.

When "REMOTE OPERATION MODE" is displayed on the LCD panel, the inverter start

operation can only be performed remotely. If local inverter start operation is required (at the

UPS), select "LOCAL ONLY" or “REMOTE & LOCAL” in the OPERATION MENU.

!

NOTE

!

NOTE