Introduction

This appendix lists the tasks for installing a SmartNode 4900 IpChannel Bank (see

table 18

). Make a copy of

this checklist and mark the entries as you complete each task. For each IpChannel Bank, include a copy of the
completed checklist in your site log.

Table 18. Installation checklist

Task

Verified by

Date

Network information available & recorded in site log

Environmental specifications verified

Site power voltages verified

Installation site pre-power check completed

Required tools available

Additional equipment available

All printed documents available

SmartWare release & build number verified

Rack, desktop, or wall mounting of chassis completed

Initial electrical connections established

ASCII terminal attached to console port

Cable length limits verified

Initial configuration performed

Initial operation verified