General, Venting, Install vent and combustion air piping – Lochinvar Sync Condensing Boiler 1 User Manual

Page 15

background image

15

Installation & Operation Manual

2

General

venting

(continued)

This appliance requires a special venting
system. Use only approved stainless steel,
PVC, CPVC or polypropylene pipe and
fittings listed in Tables 2C, 2D, and 2F for
vent pipe, and fittings. Failure to comply
could result in severe personal injury,
death, or substantial property damage.

Installation must comply with local
requirements and with the National
Fuel Gas Code, ANSI Z223.1 for U.S.
installations or CSA B149.1 for Canadian
installations.

Install vent and combustion air piping

ƽ DANGER

The SYNC boiler must be vented and
supplied with combustion and ventilation
air as described in this section. Ensure the
vent and air piping and the combustion
air supply comply with these instructions
regarding vent system, air system, and
combustion air quality. See also Section 1
of this manual.
Inspect finished vent and air piping
thoroughly to ensure all are airtight and
comply with the instructions provided and
with all requirements of applicable codes.
Failure to provide a properly installed vent
and air system will cause severe personal
injury or death.

ƽ WARNING

NOTICE

ƽ WARNING

For closet and alcove installations, CPVC,
polypropylene or stainless steel material
MUST BE used in a closet/alcove structure.
Failure to follow this warning could result
in fire, personal injury, or death.

Air intake/vent connections

1. Combustion Air Intake Connector (FIG. 2-4) - Used to

provide combustion air directly to the unit from outdoors. A

fitting is provided on the unit for final connection.

Combustion air piping must be supported per guidelines

listed in the National Mechanical Code, Section 305, Table

305.4 or as local codes dictate.

2. Vent Connector (FIG.'s 2-5 thru 2-8) - Used to provide a

passageway for conveying combustion gases to the

outside. A transition fitting is provided on the unit for

final connection. Vent piping must be supported per the

National Building Code, Section 305, Table 305.4 or as

local codes dictate.

The SYNC boiler vent and air piping can be installed through
the roof or through a sidewall. Follow the procedures in this
manual for the method chosen. Refer to the information in
this manual to determine acceptable vent and air piping length.

You may use any of the vent/air piping methods covered in this
manual. Do not attempt to install the SYNC boiler using any
other means.

You must also install air piping from outside to the boiler
air intake adapter unless following the Optional Room Air
instructions on page 18 of this manual. The resultant installation
is direct vent (sealed combustion).

ƽ WARNING

DO NOT mix components from different
systems. The vent system could fail,
causing leakage of flue products into the
living space. Mixing of venting materials
will void the warranty and certification of
the appliance.

ƽ WARNING Do not connect any other appliance to

the vent pipe or multiple boilers to a
common vent pipe. Failure to comply
could result in severe personal injury,
death, or substantial property damage.

Improper installation of venting systems
may result in injury or death.

ƽ CAUTION

Follow the instructions in Section 1, page
11 of this manual when removing a boiler
from an existing vent system.

NOTICE

Figure 2-4 Near Boiler Air Piping

AIR