beautypg.com

Guardian Technologies 4758 User Manual

Page 125

background image

SECTION 5.1

SYSTEM FUNCTIONAL TESTS

OPERATIONAL TESTS

AND ADJUSTMENTS

PART 5

Page 5.1-3

and T2. Apply an electrical load equal to the full rated
wattage/amperage capacity of the installed generator.

10.Connect an accurate AC voltmeter and a frequency

meter across terminal lugs E1 and E2. Voltage should
be greater than 230 volts; frequency should be greater
than 58 Hertz.

11.Let the generator run at full rated load for 20-30

minutes. Listen for unusual noises, vibration or other
indications of abnormal operation. Check for oil leaks,
evidence of overheating, etc.

12.When testing under load is complete, turn OFF electrical

loads.

13.Set the generator main circuit breaker to its OFF (or

open) position.

14.Let the engine run at no-load for a few minutes.

15.Set the AUTO-OFF-MANUAL switch to OFF. The engine

should shut down.

CHECKING AUTOMATIC OPERATION

To check the system for proper automatic operation,
proceed as follows:

1. Set generator main circuit breaker to its OFF (or open)

position.

2. Check that the AUTO-OFF-MANUAL switch is set to

OFF.

3. Turn off the utility power supply to the transfer switch,

using means provided (such as a utility main line circuit
breaker).

4. Manually set the transfer switch to the UTILITY position,

i.e., load terminals connected to the utility power source
side.

5. Turn ON the utility power supply to the transfer switch,

using the means provided (such as a utility main line
circuit breaker).

6. Set the AUTO-OFF-MANUAL switch to AUTO. The

system is now ready for automatic operation.

7. Turn OFF the utility power supply to the transfer switch.

With the AUTO-OFF-MANUAL switch at AUTO, the
engine should crank and start when the utility source
power is turned off. After starting, the transfer switch
should connect load circuits to the STANDBY side.
Let the system go through its entire automatic

sequence of operation.

With the generator running and loads powered by
generator AC output, turn ON the utility power supply
to the transfer switch. The following should occur:
❏ After about six seconds, the switch should transfer

loads back to the utility power source.

❏ About one minute after retransfer, the engine

should shut down.

SETTING THE EXERCISE TIMER

Your generator is equipped with an exercise timer.
Once it is set, the generator will start and exercise
once every seven days, on the day of the week and at
the time of day you complete the following sequence.
During this exercise period, the unit runs for
approximately 12 minutes and then shuts down.
Transfer of loads to the generator output does not
occur during the exercise cycle.

A switch on the control panel (see Figure 1, Page 1.6-1)
allows you to select the day and time for system
exercise. To select the desired day and time of day, you
must perform the following sequence at that time.

1. Verify that the AUTO-OFF-MANUAL switch is set

to AUTO.

2. Hold down the set timer switch until the generator starts

(approximately 10 seconds) and then release.

3. The generator will start and run for approximately 12

minutes and then shut down on its own. The exerciser
will then be set to run at that time of day every week.

NOTE: The exerciser will only work in the AUTO
mode and will not work unless this procedure is
performed. The exerciser will need to be reset every
time the 12 volt battery is disconnected and then
reconnected. The exerciser WILL NOT work if dip
switch 2 (REMOTE NOT AUTO) on the controller
printed circuit board is “ON.”

This manual is related to the following products: