Material Lifting Configuration
Set up

1 Turn the key switch to the off position.

2 Remove the pin that secures the material lifting

hook to the base. Remove the material lifting
hook and replace the pin.

3 Disconnect the running lights and the platform

controls from the platform.

4 Remove the platform controls. Open the clamp

on the back of the platform controls and slide
the controls up and off.

5 Open the controls side turntable cover.

6 Disconnect the electrical cord on the bottom

right side of the ground control box. Connect the
platform control cord disconnected in step 3 to
the ground control box. Close the turntable
cover.

7 Support the platform. Remove the toggle pin that

secures the platform to the jib boom.

8 Lift the platform up and remove it from the

machine.

9 To install the material lifting hook, insert the

bottom rail into the platform mounting bracket
and rotate up into position. Insert the toggle pin.

10 Operate the material lifting hook from the ground

with the platform controls. The key switch
should be turned to the platform control position.

11 Reverse the above process to install the

platform and return the machine to a personnel
lifting configuration.

OPERATING INSTRUCTIONS

Material Lifting Configuration

Observe and Obey:

Maintain safe distances between the operator,

the machine and fixed objects.

Be aware of the direction the boom will travel

when using the platform controls.