beautypg.com

Installing fiber management tray (optional) – H3C Technologies H3C S9500E Series Switches User Manual

Page 63

background image

53

NOTE:

SFP+ cables are hot swappable.

When connecting an SFP+ cable, make sure the bend radius of the cable is no less than eight times of
the diameter of the cable.

Figure 51 SFP+ cable

(1) Connector

(2) Pull latch

To connect an SFP+ cable:

1.

Wear an ESD-preventive wrist strap and make sure it makes good skin contact and is well
grounded.

2.

Unpack the SFP+ cable.

3.

Insert one end of the plug of the SFP+ cable horizontally into the SFP+ slot on the switch and the
other end of the plug into the SFP+ slot of the peer device.

Installing fiber management tray (optional)

NOTE:

The installation method described below is based on an N68 rack. The installation procedure is only for
your reference if you use a non-N68 rack.

A fiber management tray (FMT) is installed in a rack for winding redundant fibers between the S9500E

switches and other devices.

1.

Preparations
Confirm the following prerequisites:

{

The rack is fixed.

{

The switch is installed.

The installation involves the following materials:

{

FMT

{

M5×10 self-tapping screws (two screws for one FMT)

2.

Installation procedure
To install the fiber management tray, follow these steps, as shown in

Figure 52

.

a.

Align the FMT and the installation holes on the column of the rack.

b.

Use a Phillips screwdriver to fix each FMT with two M5×10 self-tapping screws.