Inst alla tion, Check point #6, With outlet box, or – Kohler custom Bodyspa 116347-2 User Manual
Page 17: Without outlet box
116347Ć2Ć
AA
(A)
18
Kohler Co., Kohler, WI
Check Point #6
-
GFCIĆprotected electrical power supplied to pump box (120 V,
20 A).
-
Keypad cable installed and connected to the control box,
-
With outlet box, or
-
Without outlet box.
INSTALL WATERPROOFING
MEMBRANE OR COMPOUND
WARNING: Risk of property damage and
concealed leakage. To achieve a watertight
BodySpa installation, it is critical that you
install the waterproofing membrane or applied
compound according to the material
manufacturer's instructions. Kohler Co. will not
be liable for damage caused by waterproofing
materials that are improperly installed or
sealed.
NOTE: The waterproofing membrane or applied
compound and the cement board can be installed in
any order you prefer, as long as they are installed
exactly as directed. Follow all material
manufacturer's instructions.
Install a waterproofing membrane or applied
compound to the entire floor and wall surfaces (up to
the ceiling).
Although some membranes can be installed directly
to the stud framing, we suggest you install a plywood
backing behind the membrane at least to the height of
the basin threshold.
INSTALL SUCTION BUSHING
Use a 3Ć1/4Ćinch hole saw to carefully cut a hole in
the waterproofing membrane and plywood
backing at the suction inlet location.
Press the spacer fully into the suction housing
inlet.
Apply silicone sealant to the bushing flange
surface, and insert the bushing through the
suction hole. Partially thread the nut to the
bushing. Do not tighten. Apply silicone sealant to
the end threads of the bushing, and carefully
thread the bushing to the housing until hand
tight. Wrench tighten an additional 1/4 turn. Do
not overtighten. Wrench tighten the nut against
the plywood backing. Do not overtighten.
Remove any excess sealant.
INST
ALLA
TION